Creation of an order preparation logistics centre for 30,000 lines/month over 1,700 parts - site reindustrialisation
Wednesday 17 December 2008
by
by
The estimated profit from the solution is €300k/year on an investment of €130k
Methods used:
audit and evaluation of flow
head of complete project, drawing up of specifications manuals and invitations to tender, follow up of supplier offers, planning
study of supplier stocks, coverage and rotation
analysis and integration of a picking solution (order preparation), bar codes in the ERP EQUATION by RF terminals to reach 120 to 130 lines per day per person, replenishment of stocks and supplies
analysis of ERP modification and supplier invitations to tender for a bar code solution
study of the stock transfer in France.